 |
Floats
In the
simple network below the critical path is shown in red.

Any
activity that is not a critical activity can be extended or delayed by a
certain amount without delaying the completion of the project. For
example, activity C should start after 4 months and be finished after 6
months. However, the finish could be delayed by 2 months, i.e.
until the end of month 8, without affecting the completion time of the
project as a whole. We say that activity C has a total float of 2 weeks.
The
total float of an activity is the
amount of time by which it may be extended or delayed without delaying
completion of the project, assuming no extension or delay in any other
activity. A critical activity can be defined as one which has a
total float of zero.
There
are two other types of float that are sometimes used. To
understand these, suppose the durations are changed in the example
above. The critical path is now A-C of duration 8 months, B now
has a total float of 2 and D has a total float of 1.

 |
The
free float of an activity
takes into consideration the effect on subsequent activities of a
delay. If B is delayed by 2 months it removes the spare time
that was available for D, since if D was now also delayed by 1 the
total project duration would extend to 9 months. However, B
can be delayed by 1 month without reducing the spare time for any
subsequent activity. Therefore, B has a free float of 1
month. D also has a free float of 1. |
 |
The
independent float of an
activity is calculated assuming the worst circumstances, i.e. the
activity's predecessors finish at their latest times and we want subsequent
activities to begin at their earliest times. If this is
possible, and there is still time to spare, then this is called
independent float. The free float of 1 month for B is also
an independent float. However, assuming the worst scenario
in which B is delayed by 2 months then D cannot be delayed at
all. Hence D has an independent float of 0. |
|