In an AON
network the activities are represented by rectangular nodes. The
rectangle can be sub-divided to show all the important information about
the activity:

In the
example below, activity G cannot start until the project has been
in progress for 11 months. G takes 5 months to complete.
Because of slack later in the project, the start and finish times of G
may be delayed by up to 2 months.

|